Projects
> MV “BOXY LADY” - 2011

The ship under Maltese flag underwent repair works within August - September 2011, the main works being the following:

 

  1. Regular dry dock works: anchor chains, sea valves, sea chest, tail shaft and rudder mesurements, stern tube sealing system (aft part) overhauling;
  2. External hull treatment (total area of 15,760 sqm): HPFW washing, SA1 & SA2 grit blasting 20%, 2T/U and 2F/C paining.
  3. Treatment works on hatch covers rubber channel, SA2 grit blasting and 1F/C ~ 440 sqm painting.
  4. HPFW washing of 7 ballast tanks ~1,270 sqm.
  5. 2F/C painting and steel renewal in ballast tanks ~1500 mp.
  6. Steel renewal in multiple locations ~ 29.6 tons.
  7. Piping works ~ 20 rm.
Various mechanical & electrical works: M/E scavenging air cooler (2 pcs.), auxiliary boiler (1 unit), windlass, electrical cables replacement ~1122 rm.

General

Type Container ship
Status finished
LOA 158.75
B 24
DWT 18,445
Customer center
> News and events
We would like to inform you that Constanta Shipyard will be present at Black Sea Defense & ...
30.04.2018
We inform you that our company will participate to Posidonia Exhibition in Athens, during 4-8 of ...
30.04.2018
On 20 April 2018, H.E. Mrs. Michèl Ramis, Ambassador of France in Romania, has visited ...
20.04.2018