Projects
> MT "LONGFIN" - 2011

During the month of July, Constanta Shipyard performed repair works on oil tanker M/T “Longfin”, the main works being listed below:

o    External hull treatment 16,187 m² (HPFWJ washing, grit blasting to SA2, painting);

o    Main Deck treatment 5,358 m² (grit blasting to SA2. LPFW washing, painting 2 coats);

o    Ballast tanks treatment: 18,812 m² (under deck area: HPFWJ washing, grit blasting to SA2/SA1, painting 1 S/C and 1 T/U);

o    Normal docking works: valves, anchors and chains, sea chests, tail shaft and rudder measurements;

o    Shell plating and forecastle deck repairs pertaining to collision damage (~7500 kg steel works) and afferent treatment;

o    Ballast tanks steel works (under main deck): ~7,500 kg and 909 pcs. smaller than 20kg

o    Pipe works: 1400 rm

Various mechanical and electrical works: Main and Auxiliary Engines, pumps, electric motors, heat exchangers, Main and Auxiliary Engines turbochargers, boilers.

General

Type Chemical / Products Tanker
Status finished
LOA 228.60
B 32.24
DWT 83,955
Customer center
> News and events
Our iconic Romanian Navy bark MIRCEA will enter within next months into a complex repair & ...
03.06.2021
On 23rd February 2021 we had the honour of being visited by Her Excellency Laurence AUER, the ...
23.02.2021
On 14th of August we have celebrated the naming ceremony of our newbuilding project 590 - MT ...
14.08.2020