Projects
> 2021-MSC DON GIOVANNI

During the hot summer of 2021 (June-July) the Shipyard completed the below scope of works to the satisfaction of one of our long lasting client:

 

  • Normal docking works:
  • Treatment and painting:
             - External Hull;
        - Cargo holds;
        - Hatch covers.

 

  •  Steel works:

               - Structural steel: up to 100 tons;

         - Hatch covers: various steel works on 29 panels moved ashore.


  • Soft steel: up to 5 tons.
  • Pipe works: up to 150 m.
  • Various mechanical and electrical works


A particular job on this project it was the reconstruction of ship's bulbous bow, the job calling for dedicated technical team (due to shape of bow), skilled riggers & steel fitters/welders and the blasting & painting team, such as the ship to be restated to her initial condition.


 

General

Type CONTAINER SHIP
Status finished
LOA 202.80
B 30.60
DWT 41 583
News & Press
> News and events
Between July 24–25, Constanța Shipyard hosted the 99th meeting of the members of the The ...
28.07.2025
For those involved in shipping (sailors, ship-builders, ship repairers) it is a well-known fact ...
26.06.2025
Between 11 and 13 June in Bucharest is taking place the General Assembly of SEA Europe (Shipyards' ...
16.06.2025