> 2020-MT "Zaruma", MT "Pichincha"

The ships are sister vessels and arrived in Constanta Shipyard at mid March (Zaruma) and end May (Pichincha), the main repair works being mentioned below:

 

  • Water Balast Sistem installation
  • Normal docking works: valves overhauling (57 pcs up to dia 500 mm), tailshaft withdrawal, propeller removal & polishing, external hull treatment and painting: grit blasting SA1/SA2 up to 10 350 sqm, 2 T/U & 2 F/C of paint application;
  • Steel works: Structural steel renewal up to 5 t;
  • Pipe works: Pipe up to 310 rm renewal
  • Mechanical & electrical works: Air coolers o/h, winch & windlass o/h (4 pcs), heat exchanger o/h - 3pc; PV valves o/h (14 pcs), mooring winch brake o/h (14 pcs).

General

Type Crude Oil Tanker
Status finished
LOA 244.25 m
B 42 m
DWT 105,093
News & Press
> News and events
Between 11 and 13 June in Bucharest is taking place the General Assembly of SEA Europe (Shipyards' ...
16.06.2025
The 171st edition of the Informal Tanker Operators' Safety Forum (ITOSF) took place on June ...
12.06.2025
Between May 20–23, 2025, Constanța Shipyard (Șantierul Naval Constanța S.A.) ...
26.05.2025