> 2020-MT "Zaruma", MT "Pichincha"

The ships are sister vessels and arrived in Constanta Shipyard at mid March (Zaruma) and end May (Pichincha), the main repair works being mentioned below:

 

  • Water Balast Sistem installation
  • Normal docking works: valves overhauling (57 pcs up to dia 500 mm), tailshaft withdrawal, propeller removal & polishing, external hull treatment and painting: grit blasting SA1/SA2 up to 10 350 sqm, 2 T/U & 2 F/C of paint application;
  • Steel works: Structural steel renewal up to 5 t;
  • Pipe works: Pipe up to 310 rm renewal
  • Mechanical & electrical works: Air coolers o/h, winch & windlass o/h (4 pcs), heat exchanger o/h - 3pc; PV valves o/h (14 pcs), mooring winch brake o/h (14 pcs).

General

Type Crude Oil Tanker
Status finished
LOA 244.25 m
B 42 m
DWT 105,093
Customer center
> News and events
Fameline Holding Group and Limassol Marina organized on the 28th of September 2024 the 8th edition ...
30.09.2024
Santierul Naval Constanta (Constanta Shipyard) is going GREEN. SNC is implementing a new ...
23.09.2024
“SMM is more than a trade fair – it is the heartbeat of this industry,” Heiko M ...
09.09.2024