Projects
> 2020-MT "Zaruma", MT "Pichincha"

The ships are sister vessels and arrived in Constanta Shipyard at mid March (Zaruma) and end May (Pichincha), the main repair works being mentioned below:

 

  • Water Balast Sistem installation
  • Normal docking works: valves overhauling (57 pcs up to dia 500 mm), tailshaft withdrawal, propeller removal & polishing, external hull treatment and painting: grit blasting SA1/SA2 up to 10 350 sqm, 2 T/U & 2 F/C of paint application;
  • Steel works: Structural steel renewal up to 5 t;
  • Pipe works: Pipe up to 310 rm renewal
  • Mechanical & electrical works: Air coolers o/h, winch & windlass o/h (4 pcs), heat exchanger o/h - 3pc; PV valves o/h (14 pcs), mooring winch brake o/h (14 pcs).

General

Type Crude Oil Tanker
Status finished
LOA 244.25 m
B 42 m
DWT 105,093
Customer center
> News and events
Santierul Naval Constanta SA (Constanta Shipyard), is continuing its steady course as a leading NB ...
11.09.2023
Following its assumed policy of continuous improvement in what consist the increase of efficiency ...
11.08.2023
COMPLEX REPAIRS & UPGRADES DURING 2022. As a prime Romanian Navy contractor, during beginning of ...
11.02.2023