> 2019-MT "VALLESINA"

The ship arrived in mid April 2019 in Constanta Shipyard, in order to perform several repair works and specific docking works.  The main works being the following:

 

•    Regular dry dock works: anchor chains cleaning, sea chest cleaning, sea valves overhauling, rudder clearances measurements, tailshaft wear down, anodes renewal;
•    External hull treatment: total area 17.000 sqm (HPFW washing, grit blasting SA1 + SA2, silicone paint application underwater area and bootop); Propeller silicone paint application
•    Retrofit installation of water Ballast Treatment System – Headway
•    Various electrical and mechanical works: ME overhauling (7 lines), pumps overhauling (16 pcs.); electric motors overhauling; load test of lifeboats and davits;


Finally, the ship left the Shipyard, upon completion of repairs according to the contractual terms, to the full satisfaction of her Owners.

General

Type Crude Oil Tanker
Status finished
LOA 243 m
B 42.02 m
DWT 109,060
News & Press
> News and events
Between 11 and 13 June in Bucharest is taking place the General Assembly of SEA Europe (Shipyards' ...
16.06.2025
The 171st edition of the Informal Tanker Operators' Safety Forum (ITOSF) took place on June ...
12.06.2025
Between May 20–23, 2025, Constanța Shipyard (Șantierul Naval Constanța S.A.) ...
26.05.2025