Projects
> 2019-MT "VALLESINA"

The ship arrived in mid April 2019 in Constanta Shipyard, in order to perform several repair works and specific docking works.  The main works being the following:

 

•    Regular dry dock works: anchor chains cleaning, sea chest cleaning, sea valves overhauling, rudder clearances measurements, tailshaft wear down, anodes renewal;
•    External hull treatment: total area 17.000 sqm (HPFW washing, grit blasting SA1 + SA2, silicone paint application underwater area and bootop); Propeller silicone paint application
•    Retrofit installation of water Ballast Treatment System – Headway
•    Various electrical and mechanical works: ME overhauling (7 lines), pumps overhauling (16 pcs.); electric motors overhauling; load test of lifeboats and davits;


Finally, the ship left the Shipyard, upon completion of repairs according to the contractual terms, to the full satisfaction of her Owners.

General

Type Crude Oil Tanker
Status finished
LOA 243 m
B 42.02 m
DWT 109,060
News & Press
> News and events
Rotterdam, 4–7 November 2025 — Europort, hosted in the world port city of Rotterdam ...
10.11.2025
Between July 24–25, Constanța Shipyard hosted the 99th meeting of the members of the The ...
28.07.2025
For those involved in shipping (sailors, ship-builders, ship repairers) it is a well-known fact ...
26.06.2025