The ship arrived in mid April 2019 in Constanta Shipyard, in order to perform several repair works and specific docking works.  The main works being the following:

 

•    Regular dry dock works: anchor chains cleaning, sea chest cleaning, sea valves overhauling, rudder clearances measurements, tailshaft wear down, anodes renewal;
•    External hull treatment: total area 17.000 sqm (HPFW washing, grit blasting SA1 + SA2, silicone paint application underwater area and bootop); Propeller silicone paint application
•    Retrofit installation of water Ballast Treatment System – Headway
•    Various electrical and mechanical works: ME overhauling (7 lines), pumps overhauling (16 pcs.); electric motors overhauling; load test of lifeboats and davits;


Finally, the ship left the Shipyard, upon completion of repairs according to the contractual terms, to the full satisfaction of her Owners.

General

Type Crude Oil Tanker
Status finished
LOA 243 m
B 42.02 m
DWT 109,060
News & Press
> News and events
Between July 24–25, Constanța Shipyard hosted the 99th meeting of the members of the The ...
28.07.2025
For those involved in shipping (sailors, ship-builders, ship repairers) it is a well-known fact ...
26.06.2025
Between 11 and 13 June in Bucharest is taking place the General Assembly of SEA Europe (Shipyards' ...
16.06.2025