The ship arrived in Constanta Shipyard at the end of November, main repair works being mentioned below:

 

  • External hull treatment, total area of 11,070 sqm of HPFW washing, SA2 grit blasting – total area of 1,141 sqm, air blowing, T/U & F/C multiple coats painting;
  • Main deck treatment, total area of 18,000 sqm (HPFW washing and T/U & F/C painting)
  • Regular dry dock works: sea valves, anchor / chains, sea chest, tail shaft withdrawal and rudder clearances mesurements;
  • Steel works of approx. 13 t: rudder blade extension, antipiracy measures, repositioning of stopper and mooring roller, A deck hand rail reconditioning.
  • Piping works: replacement of approx. 1,300 rm of pipe, modification of Low Sulf system;
  • Various electrical and mechanical works: LSDO system upgrade.

 

Repair works were finished three days earlier.

 

General

Type Chemical / Products Tanker
Status finished
LOA 179.96
B 32.20
DWT 41,000
Customer center
> News and events
Between May 20–23, 2025, Constanța Shipyard (Șantierul Naval Constanța S.A.) ...
26.05.2025
For two days (24th and 25th of April 2025), services & ship-repairs worldwide companies met in the ...
28.04.2025
On 12th of November 2024, after completion of her commercial obligations and having finalized the ...
22.11.2024