Projects
> 2011-MT HISTRIA PRINCE

The ship arrived in Constanta Shipyard at the end of November, main repair works being mentioned below:

 

  • External hull treatment, total area of 11,070 sqm of HPFW washing, SA2 grit blasting – total area of 1,141 sqm, air blowing, T/U & F/C multiple coats painting;
  • Main deck treatment, total area of 18,000 sqm (HPFW washing and T/U & F/C painting)
  • Regular dry dock works: sea valves, anchor / chains, sea chest, tail shaft withdrawal and rudder clearances mesurements;
  • Steel works of approx. 13 t: rudder blade extension, antipiracy measures, repositioning of stopper and mooring roller, A deck hand rail reconditioning.
  • Piping works: replacement of approx. 1,300 rm of pipe, modification of Low Sulf system;
  • Various electrical and mechanical works: LSDO system upgrade.

 

Repair works were finished three days earlier.

 

General

Type Chemical / Products Tanker
Status finished
LOA 179.96
B 32.20
DWT 41,000
Customer center
> News and events
Santierul Naval Constanta SA (Constanta Shipyard), is continuing its steady course as a leading NB ...
11.09.2023
Following its assumed policy of continuous improvement in what consist the increase of efficiency ...
11.08.2023
COMPLEX REPAIRS & UPGRADES DURING 2022. As a prime Romanian Navy contractor, during beginning of ...
11.02.2023