The ship arrived in Constanta Shipyard at the end of November, main repair works being mentioned below:

 

  • External hull treatment, total area of 11,070 sqm of HPFW washing, SA2 grit blasting – total area of 1,141 sqm, air blowing, T/U & F/C multiple coats painting;
  • Main deck treatment, total area of 18,000 sqm (HPFW washing and T/U & F/C painting)
  • Regular dry dock works: sea valves, anchor / chains, sea chest, tail shaft withdrawal and rudder clearances mesurements;
  • Steel works of approx. 13 t: rudder blade extension, antipiracy measures, repositioning of stopper and mooring roller, A deck hand rail reconditioning.
  • Piping works: replacement of approx. 1,300 rm of pipe, modification of Low Sulf system;
  • Various electrical and mechanical works: LSDO system upgrade.

 

Repair works were finished three days earlier.

 

General

Type Chemical / Products Tanker
Status finished
LOA 179.96
B 32.20
DWT 41,000
News & Press
> News and events
Rotterdam, 4–7 November 2025 — Europort, hosted in the world port city of Rotterdam ...
10.11.2025
Between July 24–25, Constanța Shipyard hosted the 99th meeting of the members of the The ...
28.07.2025
For those involved in shipping (sailors, ship-builders, ship repairers) it is a well-known fact ...
26.06.2025