> 2021-MT RIVERA

A challenging retrofitting project of scrubber installation was performed on board of one of our traditional customers, between mid-September-mid October 2021.

 

SCRUBBER SYSTEM RETROFFITING

 

  • Steel works:

- structural steel: up to 60 tons;

- soft steel: foundations up to 11 tons:

 

  • Treatment works:
      -Scrubber casing/foundation; outfitting- ladders, handrails, access platforms;  
            galvanized pipes-scrubber casing & ER; pipes supports-scrubber casing & ER   
            External Scrubber casing.

  • Pipe works manufacture/install

      - Mild steel pipe/ Galvanized steel pipe/O/S Duplex & Stainless steel/ O/S GRE pipe 

             (more than 430 r.m. of various diameters).

 

  • Various O/S Equipment installation.

  • O/S electrical cable installation: up to 4000 m, cable connection.

  • Insulation & scaffolding.

 

 

 

General

Type Tanker
Status finished
LOA 249. 89
B 43.80
DWT 112 829
Customer center
> News and events
On 9th of February 2024 Prime Minister Marcel Ciolacu, the Minister of Labor and Social Solidarity ...
09.02.2024
Organized in the world port city of Rotterdam, Europort is the international maritime meeting place ...
24.11.2023
Santierul Naval Constanta SA (Constanta Shipyard), is continuing its steady course as a leading NB ...
11.09.2023